The short version

  • Each has a real cost: Buildots tracking depends on a BIM model maintained at construction level of detail; on a job where the model is stale or was never built for coordination, the comparison degrades and much of the value disappears.; Kojo benefits depend on distributors providing electronic catalogues and pricing, and a contractor whose main supplier will not participate is left keying quotes by hand.
  • They diverge on capability: Buildots covers Hard hat 360 capture, Kojo covers Field material requests.
  • Prices and features above were last checked on 1 September 2026.

Where they differ

Only the attributes on which Buildots and Kojo actually diverge.

Attributes where Buildots and Kojo differ
AttributeBuildotsKojo

Identical on both: starting price (On request), pricing model (quote), free tier (No), platforms (Web, iOS, Android), user rating (Not yet rated), category (Construction).

What each one covers

Drawn from each product's published feature list. An absence here means we hold no record of it - not that the product lacks it.

Only in Buildots

  • Hard hat 360 capture
  • Model to as-built comparison
  • Per activity progress scoring
  • Programme deviation alerts
  • Delay forecasting
  • Visual evidence trail
  • Subcontractor performance reporting

Only in Kojo

  • Field material requests
  • Multi-supplier quoting
  • Purchase order management
  • Inventory and warehouse
  • Committed cost visibility
  • Enterprise resource planning integration

What people use each for

The jobs each tool is most often brought in to do.

Buildots

  • A residential tower where the same fit-out sequence repeats on forty floors and the contractor wants an objective read on cycle timenot Kojo
  • A hospital or data centre fit-out where MEP first fix progress is disputed between the main contractor and trades every monthnot Kojo
  • A developer that wants independent progress evidence before certifying an interim payment applicationnot Kojo
  • A contractor building a production rate history across projects so future programmes are based on measured output rather than assumptionnot Kojo

Kojo

  • An electrical or mechanical contractor where materials are close to half of job cost and buying happens dailynot Buildots
  • A trade contractor that cannot see committed material cost against a job until the invoice arrivesnot Buildots
  • A contractor consolidating purchasing across branches to negotiate better distributor pricingnot Buildots
  • A subcontractor tracking warehouse stock and job transfers that currently live in a spreadsheetnot Buildots

Where each one falls short

Documented limitations, not opinions. Every one is a constraint you would hit in normal use.

Buildots

  • Tracking depends on a BIM model maintained at construction level of detail; on a job where the model is stale or was never built for coordination, the comparison degrades and much of the value disappears.
  • The data only arrives if someone walks the site every week with the camera, so coverage decays quietly when the site team is under pressure, exactly when the reporting is most needed.
  • Pricing is per project rather than per seat and includes hardware, so a contractor cannot roll it out cheaply across a portfolio of small jobs and it is uneconomic below a certain project value.
  • It reads interior fit-out and repetitive vertical work far better than structure, groundworks or external envelope, so a large fraction of a project's programme is outside what it can score.
  • Making progress objective creates commercial friction with subcontractors whose valuations have historically been negotiated, and contractors who deploy it without addressing that in the subcontract get pushback rather than adoption.

Kojo

  • Benefits depend on distributors providing electronic catalogues and pricing, and a contractor whose main supplier will not participate is left keying quotes by hand.
  • It serves speciality trade contractors; general contractors procure subcontracts rather than materials and get almost nothing from it.
  • Enterprise resource planning integration quality varies by system and version, so confirm the depth for your exact configuration rather than accepting the logo on the website.
  • Field adoption is the whole game, and foremen who lose signal in a plant room or basement revert to phoning the office within days unless offline capture genuinely works.
  • It changes purchasing process as well as software, so contractors whose buying authority is informal have to formalise who can commit money before the system produces clean data.

Pricing, plan by plan

Buildots

On request
  • Buildots$undefined/year
    • Priced per project by size and duration
    • Camera hardware included in the engagement
    • Model onboarding and setup quoted separately

Kojo

On request
  • Kojo$undefined/year
    • Materials procurement workflow
    • Supplier quoting and purchase orders
    • Inventory tracking

Which should you pick?

Choose Buildots if

  • You need hard hat 360 capture.
  • You work on Web, iOS, Android.
  • You also want model to as-built comparison.

Choose Kojo if

  • You need field material requests.
  • You work on Web, iOS, Android.
  • You also want multi-supplier quoting.

Questions people ask

Is Buildots or Kojo better?
Neither clearly leads. Buildots starts at On request and Kojo at On request, and user ratings are close enough to be indistinguishable. Choose on capability and platform support.
Which is cheaper, Buildots or Kojo?
Buildots starts at On request and Kojo at On request.
Does Buildots or Kojo run on more platforms?
Both run on Web, iOS, Android, so platform support will not decide this one for you.
What is Buildots best used for?
Buildots is most often used for a residential tower where the same fit-out sequence repeats on forty floors and the contractor wants an objective read on cycle time, a hospital or data centre fit-out where mep first fix progress is disputed between the main contractor and trades every month, a developer that wants independent progress evidence before certifying an interim payment application, a contractor building a production rate history across projects so future programmes are based on measured output rather than assumption. Of those, a residential tower where the same fit-out sequence repeats on forty floors and the contractor wants an objective read on cycle time and a hospital or data centre fit-out where mep first fix progress is disputed between the main contractor and trades every month are not what Kojo is typically brought in for.
What can Buildots do that Kojo cannot?
Buildots covers Hard hat 360 capture, Model to as-built comparison, Per activity progress scoring, Programme deviation alerts. Kojo covers Field material requests, Multi-supplier quoting, Purchase order management, Inventory and warehouse.

Answered from the vendors’ own pages

Buildots: What does Buildots cost?

It is quoted per project based on size, duration and scope, with camera hardware included. Nothing is published.

Kojo: Is this for general contractors?

No. It is built for speciality trade contractors buying materials. General contractors procure subcontracts and would get little from it.

Buildots: Do I need a BIM model?

Yes. The system scores progress by comparing captured conditions against model objects, so the model quality sets the ceiling on accuracy.

Kojo: What if our suppliers will not connect?

You lose most of the quoting benefit and keep only the internal workflow. Check distributor participation before purchase, because it determines the return.

Buildots: What kind of projects suit it?

Repetitive vertical work with heavy interior fit-out. Civil, groundworks and external envelope are poorly covered.

Kojo: Does it work without signal on site?

Field requests are designed for site use, and offline behaviour should be tested with your own crews in your worst locations, because that is where adoption is won or lost.

Buildots: Who does the site walks?

Your own site team, typically once or twice a week. There is no Buildots operator on site.