The short version

  • Each has a real cost: B2W Estimate pricing is not published anywhere, and the quote depends on estimator seats plus which of the four other B2W modules you take, so like-for-like comparison with HeavyBid or spreadsheets is impossible without going through a sales cycle; ProEst proest.com/pricing/ redirects to construction.autodesk.com/pricing/proest, confirming ProEst is now sold exclusively as part of Autodesk Construction Cloud rather than as a standalone product.
  • They diverge on capability: B2W Estimate covers Production-rate estimating, ProEst covers Digital takeoff.
  • Prices and features above were last checked on 1 September 2026.

Where they differ

Only the attributes on which B2W Estimate and ProEst actually diverge.

Attributes where B2W Estimate and ProEst differ
AttributeB2W EstimateProEst
Starting priceOn request$200/month
Pricing modelquotesubscription
PlatformsWindows, WebWeb
FoundedUnknown1996

Identical on both: free tier (No), user rating (Not yet rated), category (Construction).

What each one covers

Drawn from each product's published feature list. An absence here means we hold no record of it - not that the product lacks it.

Only in B2W Estimate

  • Production-rate estimating
  • Central resource database
  • Concurrent bidding
  • DOT bid file export
  • Alternates and addenda
  • Field feedback loop
  • Bid analysis

Only in ProEst

  • Digital takeoff
  • Cost databases
  • Bid management
  • Proposal generation
  • Reporting
  • Sage 300
  • QuickBooks
  • Procore

What people use each for

The jobs each tool is most often brought in to do.

B2W Estimate

  • A grading contractor bids a 40 million dollar DOT job and needs to test three crew configurations against the same quantities before the bid deadlinenot ProEst
  • A utility contractor wants the production rates used in the winning bid pushed into field logging so the superintendent is measured against the estimatenot ProEst
  • An estimating department with four estimators needs several people working on separate sections of one bid without merging spreadsheets by handnot ProEst
  • A contractor moving off HeavyBid wants a resource database it can reuse across estimating, dispatch and fleet maintenancenot ProEst

ProEst

  • Project estimatingnot B2W Estimate
  • Bid managementnot B2W Estimate
  • Cost analysisnot B2W Estimate
  • Proposal creationnot B2W Estimate

Where each one falls short

Documented limitations, not opinions. Every one is a constraint you would hit in normal use.

B2W Estimate

  • Pricing is not published anywhere, and the quote depends on estimator seats plus which of the four other B2W modules you take, so like-for-like comparison with HeavyBid or spreadsheets is impossible without going through a sales cycle
  • The system is worthless until your own crews, equipment and production rates are loaded, which is typically several months of a senior estimator's time before the first bid comes out
  • It is aimed squarely at heavy civil self-performing work, so a general contractor whose bids are mostly subcontractor quotes gets very little from the production-rate engine
  • The Trimble acquisition means the product now competes internally with other Trimble civil estimating assets, and buyers should ask directly about the long term roadmap for overlapping products before signing a multi-year term
  • Reporting outside the Inform module is limited, so organisations that want bid analytics across years typically end up buying another module or extracting to a warehouse

ProEst

  • proest.com/pricing/ redirects to construction.autodesk.com/pricing/proest, confirming ProEst is now sold exclusively as part of Autodesk Construction Cloud rather than as a standalone product.

Pricing, plan by plan

B2W Estimate

On request
  • B2W Estimate$undefined/year
    • Priced per estimator seat with a separate server or hosting component
    • Additional B2W modules quoted separately
    • Implementation and resource database setup billed as a project

ProEst

$200/month
  • ProEst Estimating$200/month
    • Digital takeoff
    • Pre-built assemblies
    • Bid management
  • EnterpriseFree
    • Advanced integrations
    • Custom assemblies
    • Multi-company

Which should you pick?

Choose B2W Estimate if

  • You need production-rate estimating.
  • You work on Windows, Web.
  • You also want central resource database.

Choose ProEst if

  • You need digital takeoff.
  • You also want cost databases.

Questions people ask

Is B2W Estimate or ProEst better?
Neither clearly leads. B2W Estimate starts at On request and ProEst at $200/month, and user ratings are close enough to be indistinguishable. Choose on capability and platform support.
Which is cheaper, B2W Estimate or ProEst?
B2W Estimate starts at On request and ProEst at $200/month.
Does B2W Estimate or ProEst run on more platforms?
B2W Estimate runs on Windows, Web. ProEst runs on Web.
What is B2W Estimate best used for?
B2W Estimate is most often used for a grading contractor bids a 40 million dollar dot job and needs to test three crew configurations against the same quantities before the bid deadline, a utility contractor wants the production rates used in the winning bid pushed into field logging so the superintendent is measured against the estimate, an estimating department with four estimators needs several people working on separate sections of one bid without merging spreadsheets by hand, a contractor moving off heavybid wants a resource database it can reuse across estimating, dispatch and fleet maintenance. Of those, a grading contractor bids a 40 million dollar dot job and needs to test three crew configurations against the same quantities before the bid deadline and a utility contractor wants the production rates used in the winning bid pushed into field logging so the superintendent is measured against the estimate are not what ProEst is typically brought in for.
What can B2W Estimate do that ProEst cannot?
B2W Estimate covers Production-rate estimating, Central resource database, Concurrent bidding, DOT bid file export. ProEst covers Digital takeoff, Cost databases, Bid management, Proposal generation.

Answered from the vendors’ own pages

B2W Estimate: Is B2W Estimate still sold under its own name?

Yes. Trimble acquired B2W in 2022 and continues to sell it as B2W Estimate within the Trimble Construction portfolio.

B2W Estimate: Is there a perpetual licence?

Current sales are subscription based. Existing perpetual customers have been migrated toward subscription, so treat a perpetual arrangement as something to negotiate rather than assume.

B2W Estimate: How does it compare with HeavyBid?

Both are production-rate estimators for heavy civil. B2W's argument is the shared resource database across estimating, field tracking, dispatch and maintenance; HeavyBid's is depth of bidding features and a large installed base in highway work.

B2W Estimate: Does it work for building construction?

Poorly. It assumes self-performed work priced by crew output. Vertical builders bidding mostly subcontracted scopes should look elsewhere.