The short version

  • Each has a real cost: ALICE Technologies the output is only as good as the recipes, and building accurate recipes is specialist modelling work most contractors cannot staff, so engagements depend on ALICE or a consultant doing it, which turns software into a services contract.; Buildots tracking depends on a BIM model maintained at construction level of detail; on a job where the model is stale or was never built for coordination, the comparison degrades and much of the value disappears.
  • They diverge on capability: ALICE Technologies covers Generative scheduling, Buildots covers Hard hat 360 capture.
  • Prices and features above were last checked on 1 September 2026.

Where they differ

Only the attributes on which ALICE Technologies and Buildots actually diverge.

Attributes where ALICE Technologies and Buildots differ
AttributeALICE TechnologiesBuildots
PlatformsWeb, WindowsWeb, iOS, Android

Identical on both: starting price (On request), pricing model (quote), free tier (No), user rating (Not yet rated), category (Construction).

What each one covers

Drawn from each product's published feature list. An absence here means we hold no record of it - not that the product lacks it.

Only in ALICE Technologies

  • Generative scheduling
  • Recipe modelling
  • Optioneering
  • Schedule recovery
  • Resource levelling
  • 4D visualisation
  • P6 and MS Project import
  • Scenario comparison reports

Only in Buildots

  • Hard hat 360 capture
  • Model to as-built comparison
  • Per activity progress scoring
  • Programme deviation alerts
  • Delay forecasting
  • Visual evidence trail
  • Subcontractor performance reporting

What people use each for

The jobs each tool is most often brought in to do.

ALICE Technologies

  • A data centre programme where six months of earlier energisation is worth more than the entire construction management budget, and the owner wants evidence that a proposed sequence change actually delivers itnot Buildots
  • A contractor facing liquidated damages that must decide between a second shift, a second crane and resequencing, and needs the cost and duration consequence of each before committingnot Buildots
  • A bid team wanting to submit a shorter programme than competitors while proving to the client that the resource profile is achievable rather than optimisticnot Buildots
  • A delay claim where the contractor must demonstrate to a client or adjudicator what the schedule would have looked like without a specific disruptionnot Buildots

Buildots

  • A residential tower where the same fit-out sequence repeats on forty floors and the contractor wants an objective read on cycle timenot ALICE Technologies
  • A hospital or data centre fit-out where MEP first fix progress is disputed between the main contractor and trades every monthnot ALICE Technologies
  • A developer that wants independent progress evidence before certifying an interim payment applicationnot ALICE Technologies
  • A contractor building a production rate history across projects so future programmes are based on measured output rather than assumptionnot ALICE Technologies

Where each one falls short

Documented limitations, not opinions. Every one is a constraint you would hit in normal use.

ALICE Technologies

  • The output is only as good as the recipes, and building accurate recipes is specialist modelling work most contractors cannot staff, so engagements depend on ALICE or a consultant doing it, which turns software into a services contract.
  • Pricing is quoted per project or programme with no published rates, so the tool is effectively unavailable to anyone who cannot justify a bespoke enterprise negotiation.
  • It only pays back on projects where float has a high monetary value; on a mid-size commercial building the modelling effort exceeds the schedule saving, which is why the customer list skews to data centres, energy and heavy civils.
  • A generated schedule still has to be accepted by superintendents and subcontractors who did not build it, and adoption failures are usually social rather than technical: the field runs the plan it believes in.
  • The 2026 McKinsey alliance pushes distribution towards consulting-led engagements, which raises the effective cost of entry and makes the direct-purchase path less certain for a contractor that just wants a licence.

Buildots

  • Tracking depends on a BIM model maintained at construction level of detail; on a job where the model is stale or was never built for coordination, the comparison degrades and much of the value disappears.
  • The data only arrives if someone walks the site every week with the camera, so coverage decays quietly when the site team is under pressure, exactly when the reporting is most needed.
  • Pricing is per project rather than per seat and includes hardware, so a contractor cannot roll it out cheaply across a portfolio of small jobs and it is uneconomic below a certain project value.
  • It reads interior fit-out and repetitive vertical work far better than structure, groundworks or external envelope, so a large fraction of a project's programme is outside what it can score.
  • Making progress objective creates commercial friction with subcontractors whose valuations have historically been negotiated, and contractors who deploy it without addressing that in the subcontract get pushback rather than adoption.

Pricing, plan by plan

ALICE Technologies

On request
  • ALICE$undefined/year
    • Quoted per project or per programme
    • Generative scheduling and optioneering
    • Recipe modelling support

Buildots

On request
  • Buildots$undefined/year
    • Priced per project by size and duration
    • Camera hardware included in the engagement
    • Model onboarding and setup quoted separately

Which should you pick?

Choose ALICE Technologies if

  • You need generative scheduling.
  • You work on Web, Windows.
  • You also want recipe modelling.

Choose Buildots if

  • You need hard hat 360 capture.
  • You work on Web, iOS, Android.
  • You also want model to as-built comparison.

Questions people ask

Is ALICE Technologies or Buildots better?
Neither clearly leads. ALICE Technologies starts at On request and Buildots at On request, and user ratings are close enough to be indistinguishable. Choose on capability and platform support.
Which is cheaper, ALICE Technologies or Buildots?
ALICE Technologies starts at On request and Buildots at On request.
Does ALICE Technologies or Buildots run on more platforms?
ALICE Technologies runs on Web, Windows. Buildots runs on Web, iOS, Android.
What is ALICE Technologies best used for?
ALICE Technologies is most often used for a data centre programme where six months of earlier energisation is worth more than the entire construction management budget, and the owner wants evidence that a proposed sequence change actually delivers it, a contractor facing liquidated damages that must decide between a second shift, a second crane and resequencing, and needs the cost and duration consequence of each before committing, a bid team wanting to submit a shorter programme than competitors while proving to the client that the resource profile is achievable rather than optimistic, a delay claim where the contractor must demonstrate to a client or adjudicator what the schedule would have looked like without a specific disruption. Of those, a data centre programme where six months of earlier energisation is worth more than the entire construction management budget, and the owner wants evidence that a proposed sequence change actually delivers it and a contractor facing liquidated damages that must decide between a second shift, a second crane and resequencing, and needs the cost and duration consequence of each before committing are not what Buildots is typically brought in for.
What can ALICE Technologies do that Buildots cannot?
ALICE Technologies covers Generative scheduling, Recipe modelling, Optioneering, Schedule recovery. Buildots covers Hard hat 360 capture, Model to as-built comparison, Per activity progress scoring, Programme deviation alerts.

Answered from the vendors’ own pages

ALICE Technologies: What does ALICE actually produce?

A set of alternative construction sequences generated from your constraints, scored on duration, cost and resource use, so you can choose rather than accept one plan.

Buildots: What does Buildots cost?

It is quoted per project based on size, duration and scope, with camera hardware included. Nothing is published.

ALICE Technologies: Does it replace Primavera P6?

No. It imports from and exports to P6. P6 remains the contractual schedule of record on most projects.

Buildots: Do I need a BIM model?

Yes. The system scores progress by comparing captured conditions against model objects, so the model quality sets the ceiling on accuracy.

ALICE Technologies: Is the company still operating?

Yes. ALICE is active as of 2026 and announced an alliance with McKinsey in April 2026 to deliver AI scheduling to McKinsey clients.

Buildots: What kind of projects suit it?

Repetitive vertical work with heavy interior fit-out. Civil, groundworks and external envelope are poorly covered.

ALICE Technologies: How much does it cost?

Not published. It is quoted per project or programme and typically includes modelling and onboarding services.

Buildots: Who does the site walks?

Your own site team, typically once or twice a week. There is no Buildots operator on site.

ALICE Technologies: What size project justifies it?

Projects where a week of schedule has a large monetary value: data centres, energy, industrial and major infrastructure. It is hard to justify on standard commercial building work.